Home » Line your ducks up before heading to the pond

Line your ducks up before heading to the pond

Posted by Marcus McCarthy | 30 September 2014 | Construction & Infrastructure

The recent NSW Civil and Administrative Tribunal decision in The Owners – Strata Plan 69743 v TRT Constructions Pty Ltd and John & Simon Constructions Pty Ltd [2014] NSWCATCD 119 (‘J&S Constructions’) illustrates the need to be diligent before commencing and proceeding with a matter, irrespective of the jurisdiction.

The Owners Corp commenced proceedings in October 2009 in the CTTT (now NCAT), claiming defects of around $300,000.00 (just estimated at the time). By April 2013, through lack of progress between the parties, the Respondent sought a strike out of the application, this was granted by the Tribunal, but subsequently overturned by the District Court.

Come 2014, the Applicant had finalised their expert report and alleged defects valuing them at around $800,000.00. The Tribunal has a jurisdictional limit of $500,000.00 so the matter was transferred to the Supreme Court of NSW. The Tribunal noted that this entire process could have been avoided if the Applicant had correctly articulated their claim and quantum in the first instance.

Ultimately the matter is now (5 years later) in the Supreme Court, and the matter is only just commencing. The Applicant has been ordered to pay the costs of the Respondent on an ordinary basis thrown away by the transfer, plus the costs of the costs application the basis of this decision.  This is despite the matter still being before the courts and the claim ongoing.Ducks2

This case highlights the impact of not firstly considering the quantum of the claim and the alleged damage – including obtaining appropriate evidence around the same, whilst also putting an onus on the parties (the Applicant in particular) to progress matters diligently. This onus exists even if the parties are attempting to negotiate a resolution. The Tribunal has a direction to push matters towards determination, and now makes orders for the parties to do the same. It is critical that parties consider the potential need for legal representation, and the potential consequences in not progressing the matter expeditiously.

For any construction matters, including home building dispute enquiries, please contact our Construction Team on +612 4961 0002 | +612 9016 0141.

This publication is © Nexus Lawyers Pty Ltd and is for general guidance only. Legal advice should be sought before taking action in relation to any specific issues.

Related Articles

Construction Law Update 2020

31 October 2019 | Civil Contractors and Construction |

Construction law is an ever-changing landscape, which is why we work closely with our valued clients to stay ahead of the game. Here are some of the recent changes affecting the industry.

Issues of Consent – Is it better to ask forgiveness, than permission?

22 October 2019 | Construction & Infrastructure |

So, is it better to ask for forgiveness than consent? As a planning strategy it is fraught with risk, too much risk to even consider it.

NSW Security of payment changes – what you need to know.

24 September 2019 | Civil Contractors and Construction |

Is your civil construction business ready for the new security of payment reforms? You have until 21 October 2019 to get organised.

OUR AWARDS